Bureau of Land Management Field Office

Short notice. Crews spread across the state. Building got its final on time.

Project Details

Project Type Commercial HVAC
Industry Government & Municipal Facilities
Location Tillamook
Timeline 1 - 3 Months

The Job

Shuffled the schedule. Eight people, different strengths. Divided the work to match. Sheet metal personnel stepped in on insulation and duct runs. When the equipment was ready to fire, the control system needed internet — and the data company was months out. Sourced a cellular router, got connectivity, completed startup. Small punch list on controls after the fact. Jumped on it. Haworth keeps calling us back.

The Work

Large ductwork and refrigerant installation, controls integration, cellular connectivity workaround to meet certificate of occupancy deadline.